CO NP ROMO 407(1) Holzwarth Culvert

Due: 4 days leftSolicitationOpen to allCO
What: Replace a six-barrel culvert with a steel girder bridge on Holzwarth Access Road in Rocky Mountain National Park. Work includes removing existing culvert, constructing new steel bridge with concrete deck, building abutments and micropiles, temporary stream diversion, riprap, roadway surfacing, and relocating electrical line and historic head gates. Project duration: December 2026 to November 2027. Estimated cost: $700,000 to $2,000,000. Buyer: Federal Highway Administration Where: Grand Lake, Colorado (Rocky Mountain National Park, approximately nine miles north, US Highway 34) Deadline: October 27, 2026 Who can bid: Any responsible business may bid, including large companies. There is no small business set-aside. Key requirements: Not stated in the notice summary Check before bidding: Full scope of work and technical specifications in attachments; bonding, insurance, and wage determination requirements Next step: Obtain the complete solicitation documents and verify you can meet all technical and legal requirements before submitting your bid.
Buyer
FEDERAL HIGHWAY ADMINISTRATION
Place of performance
Grand Lake, CO, 80447
Response deadline
Tuesday, October 27, 2026 at 4:00 PM ET
NAICS code
237310
Contracting contact
Denise Martinez · CFLAcquisitions@dot.gov

Original description

SOLICITATION ID: 6982AF27B000004 PROJECT NUMBER: CO FTNP ROMO 407(1) PROJECT NAME: Holzwarth Culvert PROJECT DESCRIPTION: This project will replace the deficient Holzwarth Culvert (Structure No. 1520-029S), a six-barrel corrugated metal arch pipe culvert on the Holzwarth Access Road with a steel girder bridge. Located in Rocky Mountain National Park, approximately nine miles north of Grand Lake, CO, along US HWY 34 at an elevation of 8,900 feet, the culvert conveys flow from the Colorado River and provides access to the Holzwarth Historic Site. The purpose of this project is to prevent future roadway damage and flooding while maintaining access to employee housing, the historic site, and National Park Service and Forest Service recreation opportunities. SCOPE OF THE WORK: The project will consist of removal of the existing six barrel culvert and construction of a new steel girder bridge with a cast in place concrete deck. New bridge abutments and micropiles. Temporary stream diversion and riprap. New aggregate roadway surfacing. Relocation of an existing electrical line. Relocation of existing historic head gates into a new concrete slab. The site is accessible on foot a quarter mile past the locked gate at the south end of the Holzwarth Historic Site Parking Lot and along the Holzwarth Culvert Access Road. The Holzwarth Culvert Access Road is approximately 13’ wide with tight turns. Temporary widening will be necessary to prevent truck off tracking on to sensitive environmental resources. A temporary truck turnaround will also be necessary as no construction access is allowed more than 100’ west of the bridge. PRINCIPAL WORK ITEMS: 20304-2000 Removal of Bridge: 1 EACH 30202-2000 Roadway Aggregate, Method 2: 120 TON 55504-0000 Prefabricated Steel Bridge (10’ wide x 48’ long modular steel vehicular bridge): 1 LPSM 56701-0000 Micropile (8.68” dia.): 180 LNFT 62801-0000 Temporary Stream Diversion: 1 LPSM ANTICIPATED SCHEDULE: Advertisement – September 2026 Award – December 2026 NTP – December 2026 Contract Completion – November 2027 ESTIMATED COST RANGE: Total estimated cost between $700,000 and $2,000,000.